A document that outlines weights, crane configuration, and rigging requirements for a lift is referred to as what?

Prepare for the NCCER Ironworker Test. Use flashcards and multiple choice questions with hints and explanations. Get ready for your exam!

A document that outlines weights, crane configuration, and rigging requirements for a lift is known as a lift plan. This document serves as a crucial tool in planning and executing a lifting operation safely and effectively. It details the specific parameters of the lift, ensuring that all involved parties understand how the load will be lifted, what equipment will be used, and how the lift should be conducted to minimize risks.

Lift plans are tailored to each specific lifting operation and incorporate information about the load's weight, the type of crane being used, the configuration of the rigging, safety measures, and any potential hazards in the surrounding area. By documenting this information, the lift plan promotes safety and efficiency, and it is often a requirement before any lifting operation can take place.

In contrast, safety plans typically encompass broader workplace safety policies and procedures beyond just lifting operations. Project overviews provide general information about the project but do not focus specifically on the details concerning lifting operations. Inspection reports are records of the condition and functionality of equipment but do not guide specific procedures for conducting lifts. Therefore, the lift plan stands out as the correct answer due to its defined purpose in the context of lifting operations.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy